The LAX project, originally slated to open in 2023, likely will not be finished until April 2025 and the Inglewood project likely will miss the 2028 Olympics.
The Automated People Mover train is seen above the terminal loop at LAX in this rendering. Two separate automated transit systems slated to whisk riders to LAX and to SoFi Stadium in Inglewood now face delays that could push each of their openings out by more than a year.
“The project has experienced extended construction delays, prolonged dispute resolution, and difficulties in the parties’ working relationship,” the report states. “Although significant construction progress has been made, the project is required to undergo a rigorous testing and commissioning process and is not expected to be completed until April 2025.”
In an email, a spokesperson said LAWA is “in active discussions with the Automated People Mover contractor to resolve outstanding claims and has no additional information at this time.” Inglewood OKs plan displacing 41 businesses to make way for people mover to sports, entertainment venuesfrom federal, state and local sources. A joint powers authority, formed by the city and the Los Angeles County Metropolitan Transportation Authority, is expected to select the team that will implement the project from three prequalified bidders later this summer.
Indonesia Berita Terbaru, Indonesia Berita utama
Similar News:Anda juga dapat membaca berita serupa dengan ini yang kami kumpulkan dari sumber berita lain.
SoFi’s share price barely budges despite fantastic Q2SoFi Technologies’ (SOFI) second quarter was an unmitigated success.
Baca lebih lajut »
LA City Council committee to consider $400 million for LAX People MoverThe LA World Airports Commissioners previously approved the funding on July 18, which they said is needed to address claims filed by the contractor, LAX Integrated Express Solutions, also known as …
Baca lebih lajut »
LAX People Mover's budget increases by $400 million amid legal claims; opening delayed late 2025L.A. World Airports commissioners approved an additional $400 million to settle legal claims and set a date for completion of LAX's significantly delayed Automated People Mover -- increasing the project's total cost from $2.9 billion to $3.34 billion.
Baca lebih lajut »
LAX people moverThe most important stories for you to know today
Baca lebih lajut »
LAX People Mover on track for completion after board approves extra $400 millionThe allocation will settle $550 million in past claims over the long-awaited Automated People Mover train at Los Angeles International Airport.
Baca lebih lajut »
L.A. airport commission sets a date to complete LAX People MoverThe project is set to be ready on Dec. 8, 2025, and starts moving people in January 2026.
Baca lebih lajut »