LAX People Mover's budget increases by $400 million amid legal claims; opening delayed late 2025

15071618 Berita

LAX People Mover's budget increases by $400 million amid legal claims; opening delayed late 2025
Indonesia Berita Terbaru,Indonesia Berita utama
  • 📰 ABC7
  • ⏱ Reading Time:
  • 60 sec. here
  • 2 min. at publisher
  • 📊 Quality Score:
  • News: 27%
  • Publisher: 68%

L.A. World Airports commissioners approved an additional $400 million to settle legal claims and set a date for completion of LAX's significantly delayed Automated People Mover -- increasing the project's total cost from $2.9 billion to $3.34 billion.

Airport commissioners approved an additional $400 million to settle legal claims and set a date for completion of LAX's significantly delayed Automated People Mover -- increasing the project's total cost from $2.9 billion to $3.34 billion.L.A. World Airports commissioners unanimously approved an additional $400 million to settle legal claims and set a date for completion of LAX's significantly delayed Automated People Mover -- increasing the project's total cost from $2.

"Resolution of claims now will provide LINXS the necessary cash flow and incentive to ensure schedule certainty," the report said. "It is an honor to continue our partnership with LAWA and deliver a transportation system that will offer an elevated experience for travelers and Los Angeles residents alike. Our team has worked on large and complex transit projects around the globe, and the transformation provided by the LAX People Mover is poised to truly set the bar," Shawn West, LINXS Constructors board member, said in a statement.

With the board's approval, the project is set to be completed on Dec. 8, 2025, and begin operation in January 2026. The electric train system on 2.25 miles of elevated rail with six stations will be available to ticketed passengers, their guests and airport employees for free. Councilwoman Traci Park, who represents the 11th District, including the neighborhoods around LAX, and chair of the council's tourism committee, also applauded the board's decision.

An additional $50 million was also approved as a contingency that may or may not be allocated fully, according airport officials.

Berita ini telah kami rangkum agar Anda dapat membacanya dengan cepat. Jika Anda tertarik dengan beritanya, Anda dapat membaca teks lengkapnya di sini. Baca lebih lajut:

ABC7 /  🏆 67. in US

Indonesia Berita Terbaru, Indonesia Berita utama

Similar News:Anda juga dapat membaca berita serupa dengan ini yang kami kumpulkan dari sumber berita lain.

LAX People Mover on track for completion after board approves extra $400 millionLAX People Mover on track for completion after board approves extra $400 millionThe allocation will settle $550 million in past claims over the long-awaited Automated People Mover train at Los Angeles International Airport.
Baca lebih lajut »

LAX People Mover could have completion date — and $400 million in added costsLAX People Mover could have completion date — and $400 million in added costsLos Angeles World Airports staff is asking for funds to settle claims over the delayed People Mover at Los Angeles International Airport.
Baca lebih lajut »

LAX people moverLAX people moverThe most important stories for you to know today
Baca lebih lajut »

L.A. airport commission sets a date to complete LAX People MoverL.A. airport commission sets a date to complete LAX People MoverThe project is set to be ready on Dec. 8, 2025, and starts moving people in January 2026.
Baca lebih lajut »

Airport Commission to consider another $400M for LAX People MoverAirport Commission to consider another $400M for LAX People MoverLos Angeles World Airports Commissioners on Thursday were set to consider approving an additional $400 million to settle legal claims and set a date for the…
Baca lebih lajut »

LAX Automated People Mover: Officials to consider another $400M for projectLAX Automated People Mover: Officials to consider another $400M for projectLA World Airports Commissioners Thursday will consider approving an additional $400 million to settle legal claims and set a date for completion of LAX's significantly delayed Automated People Mover.
Baca lebih lajut »