It said it finished several components of the project, including the Santander and Dapitan Cable Terminal Stations, the 350-kiloVolt submarine cable and the Lala-Aurora 138-kV transmission line. Read more👇
It said it finished several components of the project, including the Santander and Dapitan Cable Terminal Stations, the 350-kiloVolt submarine cable and the Lala-Aurora 138-kV transmission line.
“NGCP is happy to report that these critical MVIP components are now complete and ready for energization. We hope this would finish on time, but factors beyond our control required an adjustment to our project timeline. We are working double-time to complete the overhead transmission line portions and advance the project to its commissioning stage to connect the Luzon, Visayas and Mindanao grids,” the company said.
Work on the submarine cable component started in November 2018 and was originally slated to be completed in June 2021. The damage to submarine cable 1 caused by a third-party vessel also delayed construction activities, with repairs completed only in November 2021.
Indonesia Berita Terbaru, Indonesia Berita utama
Similar News:Anda juga dapat membaca berita serupa dengan ini yang kami kumpulkan dari sumber berita lain.
NBI nabs man, woman for selling lots using fake land titlesThe National Bureau of Investigation-Western Mindanao Regional Office (NBI-WEMRO) arrested two persons during an entrapment operation for allegedly selling lots using fake land titles.
Baca lebih lajut »
Trilogy: Canelo aims to finish Golovkin rivalry with a KO | The Associated PressNEW YORK—A split draw in the first fight and then a majority decision in favor of Canelo Álvarez in the second. So, how about a knockout in the third chapter to settle once and for all the fierce rivalry between the Mexican superstar and Gennady Golovkin? “From the first round…
Baca lebih lajut »
Magnus Haven's new music video featuring Zeinab Harake trends on YouTubePop rock band Magnus Haven’s latest single “Oh Jo” is currently the top trending OPM track on YouTube.
Baca lebih lajut »
PHL to borrow P16.71B for rehab of Agus-Pulangi power plants–DOF | Bernadette D. Nicolas and Manuel CayonThe Philippines is eyeing to borrow an estimated P16.71 billion for the rehabilitation of Agus-Pulangi power plants in Mindanao as it aims to hasten the country’s shift to clean energy resources. The Department of Finance (DOF) bared on Tuesday it is now fine tuning a proposed arrangement with the Power…
Baca lebih lajut »
Peso plunges to P55:$1 levelThe Philippine peso retreated against its US counterpart on Wednesday, to mark a fresh 16-year low in line with the decline in the local equities market.The local currency lost 29 centavos to close at P55:06:$1 versus Tuesday’s finish of P54.77:$1. This is the weakest since October 27, 2005’s close of P55.08:$1.
Baca lebih lajut »
Delegating effectively | Carlo AtienzaI USED to work for someone who would give us last-minute tasks which he expected us to finish within the day. This went on for a while until several of my colleagues quit and their main reason was the workload. We found out later that he resigned for the same…
Baca lebih lajut »